Pump station work at 14th Street will cause West Avenue closure next week

The reconstruction of West Avenue has scarcely begun, and there is a big-time detour happening next week.Alton_map_022015 (1)

Starting Monday, West Avenue will be closed between 12th and 15th streets in advance of the installation of underground pump station structures and pipes at 14th Street.

The work is part of a larger project to add five new pumping stations in the Alton Road – West Avenue corridor at Fifth, Seventh, 10th, 14th and 17th streets, in addition to raising West Avenue as much as three feel to combat flooding.

For next week’s work, northbound drivers on West Avenue will have to turn east on 12th Street to Alton Road, then head north on Alton before turning left on 15th Street to return to West Avenue.

Southbound drivers will have to turn left on 15th Street, then right on Alton, right on 12th Street and left to continue south on West Avenue.

In addition there will be lane closures on 17th Street east of the Collins Canal, an inconvenience that started last week.

2 responses to “Pump station work at 14th Street will cause West Avenue closure next week

  1. Pingback: West Avenue Streetscape meeting happens tonight | Belle Isle Blog

  2. Pingback: West Avenue Streetscape meeting happens tonight | Belle Isle Blog

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s