Tag Archives: Tropical Storm Isaac

Venetian Causeway completion timetable slides to October

Five weeks ago, we reported that Miami-Dade County hoped to finish the Venetian Causeway construction project by mid-September.

The county now says the likely completion date is late October.

Why more delay in a project already nine months behind schedule?

Tropical Storm (and later hurricane) Isaac brought work to a halt. There were more suprises with underground utilities. We’ll let Miami-Dade spokeswoman Gayle Love give details:

“The Contractor has experienced further weather-related delays, as well as delays caused by the installation of the outfalls on Rivo Alto and San Marco, where unforeseen conflicts found during excavation led to the redesign of the configuration for the outfalls.  Additional delays were experienced during coordination with the City of Miami Beach for the connection of the irrigation meters to the water distribution lines in Belle Island, Rivo Alto, Di Lido and San Marino.”

Remember that workers spent days clearing equipment and debris just before Isaac moved through. Then Miami Beach Public Works had to deal with the water main break on Belle Isle on Venetian Way just west of Island Avenue.

Of course, once the main causeway work is done, construction will continue on the individual islands. And the city of Miami is building a storm-water pump stations and piping on San Marco Island, and Miami-Dade Water and Sewer is installing water mains on Biscayne Island.

Seems like it never ends.